Upper Padas Hydroelectric Project

Feasibility Study and Preparation of Tender Documents and Design

A 192 MW scheme on Upper Padas river with large RCC dam, secondary powerhouse, power tunnel, penstock and powerhouse. Dam includes a secondary powerhouse for generation of energy from environmental flow.

Norplan Hydropower has undertaken optimisation studies for this major hydropower project in Sabah in conjunction with Malaysian consultants, produced an updated project design and production of tender documents for construction of the project under an EPC Contact.

Services provided

  • Feasibility Study of secondary powerhouse.
  • SI appraisal.
  • Engineering design and final layout for EPC Contract.
  • Preparation of EPC Tender Documents.
  • Contractor Prequalification.